June 2008
The external roads, carparking areas and external lighting are now in place. The office areas are painted and although still being used as storage areas for remaining building items, there are actually only the ceiling tiles and electrical installations to complete. The office crew have already been in to measure up for desks!
The operating theatres and after-care areas are coming along. The barns and stabling are all but completed other than the external levelling and connecting to services. The building for the nursing and yard staff is pretty much completed externally, the hay and storage barns are up and the muck heap built! The paddocks are coming along and although not fenced yet, they have benefited from the recent rain and sun.
It is getting much easier to imagine the finished site and staff excitement is building at making the move.